1. Click Evaluation from the main menu.
2. Click Report Objective Progress/Results from the submenu.
3.
From
the Listing page, click the
next to the appropriate Goal to display the
Objectives associated with the Goal.
*Note: Once the objective are in view, the
becomes a
.
4.
Once
the Objectives are available, click the
to display all progress dates associated with
that Objective.

5. Click on the progress date link (e.g., 1.1) to open the progress results that you wish to edit.
6. The results will appear in the edit mode.
7. Make any changes needed to the form.
a. Status*
i. Active: the objective is currently in use.
ii. Completed: the objective has been completed.
iii. Cancelled: the objective has been cancelled and no longer used.
*Note: If Completed or Cancelled was selected, a new field will appear for you to enter the date that the objective was completed/cancelled.
8. Click Save. If you do not want to save any changes, click Cancel.